Series A is the initial draw-down from Proposition M. Bonds, in the amount of $160 million, were sold on May 2, 2007. Series B is in the amount of $174,998,901 million sold in November 2012. Series C is in the amount of $220,750,000 million sold in April 2015. Series D is in the amount of $143,300,000 million.
Following is a listing of the projects tied to Master Plan 2022 and the Governing Board resolution calling for the approval by the voters of Proposition M.
Prop M Bond Information – GBR Numbering
| Project Name | Bond Series | Project Phase | Project Budget |
|---|---|---|---|
| A Building Renovation | C | Completed | $2.7M |
| Arboretum Phase I | C | Completed | $3.4M |
| Athletics Phase I Stadiums | C | Completed | $29M |
| Athletics Phase II Fieldhouse | D | Construction | $29M |
| Baseball Field | A | Completed | $10.3M |
| Early Childhood Education Lab School | A | Completed | $17.1M |
| Escondido Education Center | A | Completed | $15.7M |
| Fallbrook Education Center | D | Construction | $54M |
| Fallbrook Education Center Interim Village | C | Completed | $29.8M |
| Health Sciences Building | A | Completed | $11M |
| Horse Ranch Creek Road | A | Completed | $10M |
| Humanities Building | B | Completed | $46M |
| Humanities Secondary Effects | B | Completed | $2.9M |
| Industrial Technology Center | A | Completed | $13.8M |
| Library/Learning Resource Center | A | Completed | $67.3M |
| Maintenance & Operations Complex | C | Completed | $18.1M |
| Parking Structure/College Police | C | Completed | $32M |
| Planetarium | A | Completed | $8.7M |
| Rancho Bernardo Education Center | C | Completed | $72.5M |
| Student Retention Center - LL Building Renovation | D | Planning | $24M |
| T Building Renovation | A | Completed | $16M |
| T Building Storage | C | Completed | $2M |
| Teaching & Learning Center (TLC) | A | Completed | $4.3M |
| Theatre/Performing Arts Complex | A | Completed | $22.7M |