The New Palomar College Planetarium
Timeline of Events

2006

 

2008

 

2009

 

2010 - 2011

 

2012

Nov.
2006

April
2008

May
2008

July
2008

May
2009

July
2009

Dec.
2009

Feb.
2010

Mar/Apr
2010

May
2010

June 2010 through
October
2011

SPRING
2012

Prop. M public bond measure passes funding new construction for Palomar College including a new planetarium.

tBP Architecture is selected to design the new planetarium.

Old planetarium hosts its last show and closes after 43 years of service to the College.

Old planetarium is demolished to make way for new campus construction.


The first 3-D design renderings of the planetarium are seen.

Architectural plans were submitted to the California Division of the State Architect (DSA) for approval.

Formal presentation of the new planetarium design to the College Governing Board.

College Governing Board gives final approval for the new planetarium project.

DSA stamps out the new planetarium design plans.

College Governing Board approves the request to go out to bid on the project.

Bidding for the new planetarium takes place.

Contract award decision occurs in late April.

Ground-breaking ceremony.

CONSTRUCTION
(~18 months)

GRAND
OPENING

Funding

Design Phase

Approval Phase

Bidding

Begin

Construction

Finish

               

^
(we are here)

       